INSTALLATION PROCEDURE

Requirement for wet riser system
The wet riser system is required for building where the topmost floor is higher than 30.5 meter above the fire appliances access level. Wet riser comprises of duty pump and standby pump set which discharging water into a 150 mm pipe, A jockey pump is used to maintain pressure in the system. The water supply pipe 150 mm diameter.

Requirement for breeching inlet installation
4-way breeching inlet should be located not more than 30 meters from the nearest external hydrant outlet and not more than 1B meter from fire appliances access.

Requirement for landing valve installation
Landing valves are provided on each floor and should comply to M.S.1489: Part 1. Landing valves are located within fire access lobbies, protected staircase or other protected lobbies. It is installed not more than 750 mm above ground level. Any boxes that are to be installed for landing valves must comply with M.S.1489: Part 1.
 Fire hose of rubber lined type complete with 65 mm diameter quick coupling and nozzle be provided in a hose cradle besides each landing valve.

Here some photos for our project reference: 

3 WAY OBLOQUE LANDING VALVE

3 WAY LANDING VALVE AT THE TOP OF BUILDING

PUMP INSTALLATION OF WET RISER SYSTEM

INSTALLATION OF BREECHING INLET ALLIGNMENT

COMPLETE SET OF LANDING VALVE/ HOSE/ CRADDLE IN RISER ROOM

DRY RISER COMPLETE SET

BREECHING INLET INSTLLATION C/W EXTENDED PIPE

2 BREECHING INLET C/W CABINET

3 WAY LANDING VALVE TESTING